ASAB II - UA Emirati

About the project

Project ASAB II - Abu Dhabi - U.A. Emirates comprises thirty wells and related facilities. Basic function of dedicated process controllers is supervision and control of water injection into the wells.

Process control system is based on Siemens S5 controllers. Visualization and operator station utilize personal computers with Sinaut LSX SCADA application.


Scope of activities

Intea was involved in process control project on ASAB II during commissioning phase. Activities included:

  • live application testing
  • PLC program changes
  • operator display changes
  • preparing test protocol
  • commissioning
  • site acceptance
  • customer training
  • project documentation (partly)

Prospekt "Nafta i plin - sustavi upravljanja" u pdf obliku možete pogledati i/ili skinuti na svoje računalo ovdje.