Reference
HPP NEK - Bugarska

About the Plants

NEK system project covers 3 hydro power plants:

  • Belmeken (375MW),
  • Momina Klisura (120MW) and
  • Sestrimo (240MW).

About the Control System
Scope

Power plants are controlled by ABB DCS - process controllers and run fully automatic. Control includes: turbines, generators, breakers, transformers, subsystems etc.
Number of wired I/O signals: 5500.

Configuration

  • Process controllers - AdvantController 450 (12 units)
  • Operator stations - AdvantStation 500 OS (6 units)
  • Information Management Stations - AS500 IMS (3 units)
  • Control network MasterBus 300 and Plant network TCP/IP
  • Event/alarm printers, hardcopy printers and report printers.

INTEA Scope

  • distributed control system - SW design specification and other documentation
  • process controllers application design, programming and testing
  • operator stations application design and customizing
    SW lead engineering and coordination

INTEA Chronology

  • 1998 - DCS SW - project leading

INTEA’s work was recognized, by ABB project management as outstanding and highly professional.